STANDARD GUIDE

AI-Capable Device Pilot: A Four-Week Evaluation Plan

Five-step practical exercise: Week one: baseline and sample selection Workstream 1: week one: baseline and sample selection. Choose an observed workflow, record its current cost and error rate and agree who approves the test population. For ai-capable device pilot: a four-week evaluation plan, the test case is an approved business workflow passing between systems. The accountable team is business service owners; the reviewer needs to see how requ

INSIGHTS / Guide overview

Guide overview

Five-step practical exercise: Week one: baseline and sample selection Workstream 1: week one: baseline and sample selection. Choose an observed workflow, record its current cost and error rate and agree who approves the test population. For ai-capable device pilot: a four-week evaluation plan, the test case is an approved business workflow passing between systems. The accountable team is business service owners; the reviewer needs to see how request ID, source record, authorisation and receipt moves through the process. Deli

IT managers, operations leads and purchasing teams conducting a controlled device trial.

INSIGHTS / What you will learn

What you will learn

  1. Week 1 — define the baseline
  2. Week 2 — confirm identity and endpoint controls
  3. Week 3 — compare real work not demonstrations
  4. Week 4 — model cost and stop conditions
  5. Hand-over — produce an auditable decision
INSIGHTS / The guide

The guide

Week 1 — define the baseline

Week one: baseline and sample selection

Workstream 1: week one: baseline and sample selection. Choose an observed workflow, record its current cost and error rate and agree who approves the test population. For ai-capable device pilot: a four-week evaluation plan, the test case is an approved business workflow passing between systems. The accountable team is business service owners; the reviewer needs to see how request ID, source record, authorisation and receipt moves through the process. Deliver produce a dated baseline and excluded cases. as a working artefact with a named owner and a due date. Only use synthetic data and ask the team to describe what it has not tested.

Putting baseline and permitted data into practice

The control boundary is easiest to test when a broad group permission could expose a document or block a legitimate employee. A control that cannot be repeated under ordinary user permissions remains unproven. Record the failed condition and the person authorised to accept any temporary workaround. Look for unexpected data movement between groups or tenants rather than assuming a correct sign-in means the record is safe. Check the final record state after a deliberate negative case. Where the result is unsafe, withdraw the incorrect share, repair the policy and confirm user access. The risk owner should see the denial or correction evidence before approving further access. Before leaving the week 1 — define the baseline stage, confirm who can repeat the test and how the next team will obtain the evidence.

The handover should make sense to someone who did not design the system. Keep the operating instructions usable during an out-of-hours incident, including the contact who can stop a risky integration and the permitted manual alternative. Review repeated service failures for a common dependency or unclear ownership. Changes should produce a better diagnostic or decision path, not just another generic checklist. Where the outcome affects authorised data use, correct approvals and a reliable business outcome, the process owner and business reviewer should confirm that the user’s task can safely resume. Before leaving the week 1 — define the baseline stage, confirm who can repeat the test and how the next team will obtain the evidence.

Define the scope

  • List the source record and its business owner for an employee opening a shared project file from a newly managed laptop.
  • Confirm who may authorise a write in Microsoft 365 and endpoint management and who audits it.
  • Keep the result of attempt the document with a guest and a member whose role has just changed with document ACL, sign-in result, device compliance status and service ticket.

Week 2 — confirm identity and endpoint controls

Week two: controlled configuration

Workstream 2: week two: controlled configuration. Provide limited permissions and realistic but non-sensitive test data, with logging and an explicit manual fallback. For ai-capable device pilot: a four-week evaluation plan, the test case is an approved business workflow passing between systems. The accountable team is business service owners; the reviewer needs to see how request ID, source record, authorisation and receipt moves through the process. Deliver capture configuration, roles and change record. as a working artefact with a named owner and a due date. Only use synthetic data and ask the team to describe what it has not tested.

Putting controlled setup into practice

An ordinary success case does not establish that access based on role, device compliance and the intended shared workspace. A control that cannot be repeated under ordinary user permissions remains unproven. Record the failed condition and the person authorised to accept any temporary workaround. Separate staff, supplier and automated identities. Each should have the minimum scope necessary to complete the approved task, and privileged access needs a specific expiry and owner. Where the result is unsafe, withdraw the incorrect share, repair the policy and confirm user access. The risk owner should see the denial or correction evidence before approving further access. The outcome for the week 2 — confirm identity and endpoint controls stage is a dated record of the accepted business state and any remaining exception.

The critical access question is who can approve a change to Microsoft 365 and endpoint management. Look for unexpected data movement between groups or tenants rather than assuming a correct sign-in means the record is safe. Check the final record state after a deliberate negative case. A control that cannot be repeated under ordinary user permissions remains unproven. Record the failed condition and the person authorised to accept any temporary workaround. Where the result is unsafe, withdraw the incorrect share, repair the policy and confirm user access. The risk owner should see the denial or correction evidence before approving further access. Before leaving the week 2 — confirm identity and endpoint controls stage, confirm who can repeat the test and how the next team will obtain the evidence.

Check responsibilities

  • Confirm who may authorise a write in Microsoft 365 and endpoint management and who audits it.
  • Keep the result of attempt the document with a guest and a member whose role has just changed with document ACL, sign-in result, device compliance status and service ticket.
  • If a broad group permission could expose a document or block a legitimate employee, record who can withdraw the incorrect share, repair the policy and confirm user access.

Week 3 — compare real work not demonstrations

Week three: positive and negative tests

Workstream 3: week three: positive and negative tests. Run normal requests, withheld permissions, missing source data and interrupted service cases using an independent evaluator. For ai-capable device pilot: a four-week evaluation plan, the test case is an approved business workflow passing between systems. The accountable team is business service owners; the reviewer needs to see how request ID, source record, authorisation and receipt moves through the process. Deliver store expected versus observed results and correction cost. as a working artefact with a named owner and a due date. Only use synthetic data and ask the team to describe what it has not tested.

Demonstration procedure: open an illustrative acceptance measure entry, connect it to rollout decision, and identify the person who could approve the resulting action. Check the normal request, then reproduce an exception passing unnoticed between teams. Capture a case identifier, relevant timestamp and the reviewer’s observed result. A failure belongs in the service exception register with a measurable corrective action. The engagement partner should be able to explain how protected confidential engagement files is handled before the exercise proceeds.

Putting observed work quality into practice

Users should be able to tell whether the business task succeeded, not only whether the application responded. Review repeated service failures for a common dependency or unclear ownership. Changes should produce a better diagnostic or decision path, not just another generic checklist. Record user-confirmed task completion alongside system health. A service that appears restored but leaves the underlying record incorrect is not ready for closure. Where the outcome affects authorised data use, correct approvals and a reliable business outcome, the process owner and business reviewer should confirm that the user’s task can safely resume. The outcome for the week 3 — compare real work not demonstrations stage is a dated record of the accepted business state and any remaining exception.

Acceptance criteria should be agreed before the preferred configuration is demonstrated. An independent business participant should challenge at least one negative result and confirm whether the authorised workflow can still be completed safely. Keep document ACL, sign-in result, device compliance status and service ticket with the result. Record what the operator expected, what actually happened, who reviewed the difference and which correction followed. The record should be understandable to the workplace administrator, team owner and service desk manager, who can agree a pass, a revision or a pause based on observed outcomes. Before leaving the week 3 — compare real work not demonstrations stage, confirm who can repeat the test and how the next team will obtain the evidence.

Record a controlled result

  • Keep the result of attempt the document with a guest and a member whose role has just changed with document ACL, sign-in result, device compliance status and service ticket.
  • If a broad group permission could expose a document or block a legitimate employee, record who can withdraw the incorrect share, repair the policy and confirm user access.
  • Review task completion, access exceptions and reopened support tickets and give the acceptance decision a named owner.

Week 4 — model cost and stop conditions

Week four: benefit and safety review

Workstream 4: week four: benefit and safety review. Compare pilot outcomes with baseline while including exceptions, support hours and accessibility requirements. For ai-capable device pilot: a four-week evaluation plan, the test case is an approved business workflow passing between systems. The accountable team is business service owners; the reviewer needs to see how request ID, source record, authorisation and receipt moves through the process. Deliver build a scorecard with measurable performance and unsupported claims removed. as a working artefact with a named owner and a due date. Only use synthetic data and ask the team to describe what it has not tested.

Putting failure and exception tests into practice

A financial comparison should treat correction work and supplier change as real operating costs. Compare the current process with a limited improvement and a larger deployment. Include integration support, access reviews, correction work and the cost of reverting to the prior operating process. Use accepted completed tasks as the denominator for benefit calculations. If manual reviews rise after automation, record the extra labour instead of presenting gross time saved as a cash benefit. Report task completion, access exceptions and reopened support tickets along with support effort, and set a review date when the funding decision may be changed. The outcome for the week 4 — model cost and stop conditions stage is a dated record of the accepted business state and any remaining exception.

The economic value depends on completed work, not the number of actions the software automates. Assign a person to verify the baseline and a separate sponsor to approve any further spend. A business case is a funding decision with explicit stop conditions. Compare the current process with a limited improvement and a larger deployment. Include integration support, access reviews, correction work and the cost of reverting to the prior operating process. Report task completion, access exceptions and reopened support tickets along with support effort, and set a review date when the funding decision may be changed. Before leaving the week 4 — model cost and stop conditions stage, confirm who can repeat the test and how the next team will obtain the evidence.

Review an exception

  • If a broad group permission could expose a document or block a legitimate employee, record who can withdraw the incorrect share, repair the policy and confirm user access.
  • Review task completion, access exceptions and reopened support tickets and give the acceptance decision a named owner.
  • List the source record and its business owner for an employee opening a shared project file from a newly managed laptop.

Hand-over — produce an auditable decision

Scale, redesign or stop

Workstream 5: scale, redesign or stop. Present a three-way decision to the sponsor with the exact scope authorised and conditions for a later test. For ai-capable device pilot: a four-week evaluation plan, the test case is an approved business workflow passing between systems. The accountable team is business service owners; the reviewer needs to see how request ID, source record, authorisation and receipt moves through the process. Deliver file a decision minute, exception owner and next-review date. as a working artefact with a named owner and a due date. Only use synthetic data and ask the team to describe what it has not tested.

Putting the go/no-go decision into practice

The economic value depends on completed work, not the number of actions the software automates. Use accepted completed tasks as the denominator for benefit calculations. If manual reviews rise after automation, record the extra labour instead of presenting gross time saved as a cash benefit. Compare the current process with a limited improvement and a larger deployment. Include integration support, access reviews, correction work and the cost of reverting to the prior operating process. Report task completion, access exceptions and reopened support tickets along with support effort, and set a review date when the funding decision may be changed. The outcome for the hand-over — produce an auditable decision stage is a dated record of the accepted business state and any remaining exception.

Security evidence should come from the destination where the action takes effect. Run an access request from an identity outside the permitted role. The business action should be denied at the destination and the reason visible in the audit record. Separate staff, supplier and automated identities. Each should have the minimum scope necessary to complete the approved task, and privileged access needs a specific expiry and owner. Where the result is unsafe, withdraw the incorrect share, repair the policy and confirm user access. The risk owner should see the denial or correction evidence before approving further access. The outcome for the hand-over — produce an auditable decision stage is a dated record of the accepted business state and any remaining exception.

Confirm the next decision

  • Review task completion, access exceptions and reopened support tickets and give the acceptance decision a named owner.
  • List the source record and its business owner for an employee opening a shared project file from a newly managed laptop.
  • Confirm who may authorise a write in Microsoft 365 and endpoint management and who audits it.

Sources and further reading

Related Technology Plus resources

Consult Modern Workplace Solutions when checking the scope or supporting evidence for this plan. This reference is being used for the pilot evidence review of AI-Capable Device Pilot: A Four-Week Evaluation Plan.

Consult Apple Announces the M4 iPad Pro and New Pencil Pro on 7 May 2024 when checking the scope or supporting evidence for this plan. This reference is being used for the pilot evidence review of AI-Capable Device Pilot: A Four-Week Evaluation Plan.

Consult A Four-Week AI Collaboration Pilot for Australian SMEs when checking the scope or supporting evidence for this plan. This reference is being used for the pilot evidence review of AI-Capable Device Pilot: A Four-Week Evaluation Plan.

INSIGHTS / Practical checklist

Practical checklist

  • Inventory pilot users and workloads
  • Set device-management baseline
  • Validate encryption and remote wipe
  • Test offline and accessibility scenarios
  • Run a real comparative work task
  • Calculate lifecycle cost by role
  • Document a support escalation
  • Approve a phased rollout or stop
INSIGHTS / Key takeaways

Key takeaways

01

Week 1 — define the baseline

Week one: baseline and sample selection Workstream 1: week one: baseline and sample selection. Choose an observed workflow, record its current cost and error rate and agree who approves the test population. For ai-capable device pilot: a four-week evaluation plan, the test case is an approved business workflow passing between systems. The accountab

02

Week 2 — confirm identity and endpoint controls

Week two: controlled configuration Workstream 2: week two: controlled configuration. Provide limited permissions and realistic but non-sensitive test data, with logging and an explicit manual fallback. For ai-capable device pilot: a four-week evaluation plan, the test case is an approved business workflow passing between systems. The accountable te

03

Week 3 — compare real work not demonstrations

Week three: positive and negative tests Workstream 3: week three: positive and negative tests. Run normal requests, withheld permissions, missing source data and interrupted service cases using an independent evaluator. For ai-capable device pilot: a four-week evaluation plan, the test case is an approved business workflow passing between systems.

04

Week 4 — model cost and stop conditions

Week four: benefit and safety review Workstream 4: week four: benefit and safety review. Compare pilot outcomes with baseline while including exceptions, support hours and accessibility requirements. For ai-capable device pilot: a four-week evaluation plan, the test case is an approved business workflow passing between systems. The accountable team

05

Hand-over — produce an auditable decision

Scale, redesign or stop Workstream 5: scale, redesign or stop. Present a three-way decision to the sponsor with the exact scope authorised and conditions for a later test. For ai-capable device pilot: a four-week evaluation plan, the test case is an approved business workflow passing between systems. The accountable team is business service owners;

LET'S TALK

Good technology starts with a conversation.

Tell us what you're aiming to achieve. We can discuss your current environment, technology challenges and the right next step.

Start a conversation

Share a few details so we can understand your enquiry.

Form powered by HubSpot. Review our Privacy Policy. If the form doesn’t load, email [email protected].